Timeline

Plans will be delivered in two phases, carried out in specific periods to ensure minimal disturbance to normal Library operations. The Library will remain open throughout and maintaining Library operations at all times is a major priority.

Phase one will involve work in small, contained areas of the building, away from main reading rooms and most of the collection. We have already raised a significant proportion of the funds required, with the fundraising campaign continuing this year.

Works in phase two will mean some disruption while the lift is installed but we expect to maintain access to all floors. Temporary alternative facilities will be provided during the renovation of the 6th Floor.

Proposed Project Timeline

Public Consultation  

May – June 2024 

Planning Permission Application 

July – August 2024

Phase One Commences  

The Discovery Room and Basement Kitchen  
2025, 6-10 months 

Phase Two Commences    

The 6th Floor and Accessible Lift  
The timing of phase two will be dependent on the fundraising campaign, plans for which are underway. 