Plans will be delivered in two phases, carried out in specific periods to ensure minimal disturbance to normal Library operations. The Library will remain open throughout and maintaining Library operations at all times is a major priority.
Phase one will involve work in small, contained areas of the building, away from main reading rooms and most of the collection. We have already raised a significant proportion of the funds required, with the fundraising campaign continuing this year.
Works in phase two will mean some disruption while the lift is installed but we expect to maintain access to all floors. Temporary alternative facilities will be provided during the renovation of the 6th Floor.
Proposed Project Timeline
Public Consultation
May – June 2024
Planning Permission Application
July – August 2024
Phase One Commences
The Discovery Room and Basement Kitchen
2025, 6-10 months
Phase Two Commences
The 6th Floor and Accessible Lift
The timing of phase two will be dependent on the fundraising campaign, plans for which are underway.